October 2023

Construction Update

General

The wet weather through September has caused some challenges to earthworks operations particularly in the Southern Section (Avant Homes- Cuthelton Farm). Works have been intermittent due to the weather sensitive nature of materials won from this section; however bulk earthworks are now nearing completion. Good progress has been made in both the North Section (DHS) with the installation of approx. 62% of the combined roadside filter drainage systems and within the central section has made good progress in the period with the completion of ground improvement works adjacent to Little Denny burn and embankment construction complete to top of capping level from DHS tie in CH1160 to CH 720 Little Denny Burn.

Accommodation Works/ Fencing/ PROW Diversions

Remaining accommodation works include installation of four new water troughs and associated pipework connections to water main. We anticipate these works will commence following completion of Scottish Power diversion works.

Public Utilities

BT Openreach – BT attended site to complete the OHL diversion on Monday 14th August 2023- BT diversion works now complete.

Scottish Power:

North Section CH 1150- 860

Ongoing investigation works linked to CE-1. To date the following operations have been completed

Installation of drainage run N02/007-N02/005

Central Section CH 650-850

South Section- CH120-650

South Section Earthworks cut ongoing CH 300

Works programmed for October 23

North Section (Denny High School)

Central Section (Cuthelton Farm Area)

South Section (Avant Homes- Cuthelton Farm)

Community Benefits

Recruitment

Training – Educational Outreach

Supply Chain Development

Community