The project has faced more unsettled weather through the month of October, there have been two MET office named storm events (Storm Agnes and Storm Babette) and a period of sustained heavy rainfall of more than 100mm in 24 hours over the weekend of 6th -7th October which led to localised flooding of the culvert area of the project.
Despite these challenges the site has made steady progress through the last month. Bulk earthworks in the southern section of the site have been completed with the roundabout area reaching completed formation level on 25th October.
Little Denny Burn culvert has been installed, the waterproofing and sand carpet protection installed, and a road formed over the top of the new culvert opening up the site for embankment construction. Works have progressed well with the last remaining section of the DEAR road achieving formation level on 30th October.