January 2024

Progress Report January 2024

Progress on the DEAR project moved at pace in the final weeks on the run in to the winter break. Another section of the mainline was surfaced to binder level week beginning December 4. The Central Section culvert and Otter pass infrastructure works have been completed and the scour protection bag work walls increased to the 1:200 year storm level. The South section has progressed well with completion of remaining mainline drainage works and kerbing and gulley installation nearing completion.

Public Utilities

Permanent Scottish Water protection works undertaken December 2023 and are now concluded. Scottish Water visited the site on December 4 to witness works being undertaken.

North Section bold

Site clearance works and roundabout verge widening works completed WB January 15.

Installation of new pond outfall drainage line commenced Monday January and line is due for completion by end of the week including eight service crossings.

Offline North SUDS basin site clearance works completed by January 12, note two  days of on line works adjacent to A883 required to remove trees overhanging A883 carriageway.

Ongoing maintenance of unbound section of DEAR main line between.

 Central Section

 South Section

February 2024 Programme

North Section

Central Section

South Section