The project has received some degree of more settled weather over the period which has allowed for some excellent progress at the Little Denny Culvert structure and embankment earthworks.
Good progress was made in both the North and South sections. The South sections earthworks for the DEAR mainline have now been concluded and the road capped with capping material. Type 1 installation in the South began on Tuesday 28th November.