Despite sustained periods of heavy rainfall and associated issues with saturated ground the Contractor has largely kept pace with the construction programme through the later weeks of March and early weeks of April.
Significant progress has been made around the new SUDs basin with pond liners installed and soil backfilling completed to the basin area and earthworks profiles.
The period has seen a huge push on footpath construction works with all footpaths surfaced to at least binder level stie wide excluding the final 350m to tie into Avant Homes footpath.
All utility diversions/protection measures are now fully completed site wide.
Northern SUDS basin works.
All off site road traffic signs installed during school Easter Holiday period under TTM.
Works programmed for April/May 24
All Sections
Training
CSCS card training day including site visit for class of 10 from Denny High School to be undertaken on 30th April.