April 2024

Construction Update

Despite sustained periods of heavy rainfall and associated issues with saturated ground the Contractor has largely kept pace with the construction programme through the later weeks of March and early weeks of April.

Significant progress has been made around the new SUDs basin with pond liners installed and soil backfilling completed to the basin area and earthworks profiles.

The period has seen a huge push on footpath construction works with all footpaths surfaced to at least binder level stie wide excluding the final 350m to tie into Avant Homes footpath.

Public Utilities

All utility diversions/protection measures are now fully completed site wide.

North Section

Northern SUDS basin works.

Central Section

South Section

Off Site Signage Works

All off site road traffic signs installed during school Easter Holiday period under TTM.

Programme

Works programmed for April/May 24

All Sections

Community Benefits

Training

CSCS card training day including site visit for class of 10 from Denny High School to be undertaken on 30th April.